Manage Electrical Change Orders Before Work Expands

Trace each changed scope through request, description, price, schedule effect, authorized approval and work release. A worked example shows the arithmetic and the paper trail.

Electrical project manager and customer approving scope discussion at office table with revised plan sheets turned away

Manage electrical change orders by tracing every change through the same six links before anyone builds it: request, scope description, price, schedule effect, authorized approval and release of the work. If any link is missing, the change is a verbal favor, and verbal favors are the reason small projects end with unpaid extras and arguments about what was promised. This article describes a business process. It is not a contract template or legal advice, so have your attorney review the actual contract language.

Why the chain matters

Public procurement shows the pieces clearly. Under Federal Acquisition Regulation Subpart 43.2, a change order is a written order, issued by someone with the authority to issue it, and the contractor continues performing as changed. When a change affects price or delivery, an equitable adjustment is negotiated, often documented in a supplemental agreement. That regulation governs federal government contracts, so do not copy its terms into a private job. The structure carries over, though: a written change, from an authorized person, with price and schedule addressed. Your contract may say something different, so read it.

The same principle applies to residential customers. The FTC’s home improvement guidance advises consumers to get promises about scope, labor costs and materials in writing, which means a customer who has done their homework will expect a changed scope to be documented too.

Link What you record Typical gap
1. Request Who asked, when, how (email, call, site note) and what they asked for The field hears it and nobody tells the office
2. Scope description What is added, removed or changed, and what stays the same, referenced to the original scope Vague wording such as “extra work as needed”
3. Price Labor hours at your rate, materials with handling allowance, permit or inspection effects, and any other direct cost Missing the office and coordination time
4. Schedule effect Days added or removed, and which later activities move Price is agreed, but the date effect is not
5. Authorized approval Name and role of the approver, the date, and the form of approval (signature or defined electronic reply) Approval comes from someone who cannot approve
6. Work release Date the field is told to proceed, with the approved document attached Work begins before the document arrives

Who is allowed to approve?

At the start of each job, record who can approve scope and price changes for the customer, and who can approve for you. On commercial work, the person who asks for the extra work in the field is often not the person who can authorize payment. Put the named approver and a backup into your kickoff notes. If the field asks for something, the response is, “We will send a change request for approval and schedule impact,” not “No problem.”

Worked example (hypothetical)

A tenant fit-out has a contract price of $48,000. The tenant’s project manager asks, in a call, to add additional work in two rooms. Your office writes it up.

  • Labor: 22 hours at a $105 billing rate = $2,310.00
  • Materials: $1,340 cost × 1.12 handling allowance = $1,500.80
  • Change order amount: $2,310.00 + $1,500.80 = $3,810.80
  • Schedule effect: 2 working days added, with a note that finishing depends on the inspection date
  • Revised contract amount: $48,000 + $3,810.80 = $51,810.80

The change request is sent to the tenant’s authorized approver, who replies with a signed approval two days later. The field is released after that date. If the field started on day one, you would have worked for two days on a verbal request, and the decision about whether to pay would belong to someone else’s memory.

What an unrecorded change costs

If the same change is built with no approval and the customer disputes it, you may carry the $3,810.80 yourself and still owe the schedule effect to the rest of the job. The SBA’s finance guidance frames decisions as a cost-benefit comparison. Do that for every disputed add: compare the dollars at stake with the cost of collecting, and decide whether to push for payment or write the work off as a lesson, but decide on purpose.

Policies that keep the chain intact

  • A stop-work trigger for the field. Anything outside the written scope goes into a change request before it is done. The only exceptions are the ones your contract and your qualified personnel say cannot wait. Record them the same day.
  • A time limit. Write how long your price for a change stays valid, and when the schedule effect becomes larger as the job moves on.
  • A running log. Show each change, its status and its dollar and day effects, so the customer can see the cumulative result.
  • Review before final billing. Compare the approved changes to the invoice lines, so nothing is billed without a record and nothing earned is forgotten.

When the customer says no

Some changes are rejected. Record the rejection. If the rejected item turns out to be necessary for the original scope to work, treat it as a scope question and bring it to your qualified supervisor and the customer’s representative, rather than quietly absorbing it. Do not assume that a cost increase is a customer’s problem or yours. Decide that by reading the contract, which may allocate responsibility in a particular way.

Starter checklist

  1. Create a one-page change request form with the six links as fields.
  2. Name the customer’s approver on every job at kickoff.
  3. Give the field a rule: no work outside the written scope until a release comes from the office.
  4. Keep a change log per job, reviewed weekly.
  5. Have your attorney review how your contract treats changes, notice and payment.