Choose a roofing supplier by scoring the things that move your schedule and cash, such as credit terms, delivery reliability, material placement, returns and shortage handling, and then converting lateness into dollars before you trust a lower unit price. A supplier is part of your production system. OSHA’s roofing guide tells employers to plan ahead so that proper equipment, material and trained workers are available. If material arrives late or incomplete, the crew you scheduled and paid for waits.
What to compare
| Criterion | Question to ask | Evidence to collect |
|---|---|---|
| Unit price and quote validity | How long is the price held, and what changes it? | Written quote with date and expiry |
| Credit terms | When is payment due, and what happens to terms after a late payment? | Account agreement, not a verbal promise |
| Delivery reliability | What is the order cut-off for next-day delivery, and how often are deliveries late? | Your own delivery log |
| Placement and timing window | Can the delivery be placed where you ask, and in a window you can staff? | Written delivery instructions per job |
| Returns and restocking | What can be returned, within what period, at what charge? | Written policy |
| Shortage and damage process | How and how fast must a shortage be reported, and how is it resolved? | Written process and a named contact |
| Availability | Which items are stocked and which are special order? | Stock list and lead times |
Placement deserves a closer look. OSHA’s fall protection training standard lists the handling and storage of equipment and materials among the topics employers must cover when training workers exposed to fall hazards. That is a reason to settle, in writing, where each delivery goes and who decides, instead of leaving it to whoever is driving the truck.
A weighted scorecard (hypothetical)
Weights add to 100. Scores run from 1 (poor) to 5 (strong) and come from your evidence, not from a sales pitch.
| Criterion | Weight | Supplier A | Supplier B |
|---|---|---|---|
| Unit price | 25 | 5 | 3 |
| Credit terms | 15 | 3 | 4 |
| Delivery reliability | 20 | 2 | 4 |
| Placement and window | 10 | 2 | 4 |
| Returns and restocking | 10 | 3 | 4 |
| Shortage and damage process | 10 | 2 | 4 |
| Availability | 10 | 4 | 4 |
| Weighted total (maximum 500) | 320 | 375 |
Supplier A: 5 x 25 = 125, 3 x 15 = 45, 2 x 20 = 40, 2 x 10 = 20, 3 x 10 = 30, 2 x 10 = 20 and 4 x 10 = 40, which sums to 320. Supplier B: 75 + 60 + 80 + 40 + 40 + 40 + 40 = 375.
Turn lateness into dollars
A scorecard hides whether the cheaper supplier is cheaper. Suppose a typical order is $9,000, Supplier A’s price is 3 percent lower, and your delivery log shows 5 late deliveries out of 20 for Supplier A (25 percent) and 1 out of 20 for Supplier B (5 percent). A late delivery idles a crew for one day at a cost of $1,200.
- A’s price advantage: 0.03 x 9,000 = $270.
- A’s expected delay cost: 0.25 x 1,200 = $300. B’s: 0.05 x 1,200 = $60.
- Net: A saves $270 but costs $240 more in expected delay (300 – 60), a net advantage of $30 per order.
A $30 edge on a $9,000 order sits inside the noise of a small sample. It does not justify taking on weaker credit terms and shortage handling. Notice what happens if A’s late rate were 35 percent instead of 25: the expected delay gap grows to $360 and B becomes the cheaper choice outright. Update the numbers as your delivery log grows.
Keep the scoring honest
Three habits stop a scorecard from becoming a justification for the supplier you already like. Score before you see the totals. Let someone who did not negotiate the account check the evidence behind the lowest and highest scores. And re-score every six months, because a supplier’s reliability, staffing and policies change. If two suppliers finish within about 10 percent of each other, keep both active, with the better one getting the jobs where schedule matters most. A second account also gives you a fallback when a delivery fails, which no scorecard can show you until it happens.
Run a trial before you commit
- Split two or three real orders between candidates, if both will extend terms.
- Log promised versus actual delivery date and time, quantity received versus ordered, and the time it took to resolve any discrepancy.
- Name one person to own the supplier relationship. The SBA’s finance guidance suggests assigning someone to handle payables, and the same applies to the person who reconciles supplier statements.
- Review at 60 days and decide whether to keep a second supplier as backup.
Failure cases
- Negotiating a price and never writing down the delivery window.
- Accepting a substitution without the owner or customer approving it.
- Treating one late delivery as proof of unreliability, or ignoring a pattern because the rep is friendly.
- Single-sourcing everything, so one supplier problem stops every job.
Sources
Pages below were read on November 12, 2026. Rules, programs and warranty terms change, so confirm current details with the named agency or document before relying on them.
- U.S. Small Business Administration: Manage your finances. Supports assigning responsibility for payables and receivables and tracking money in and out.
- OSHA: 29 CFR 1926.503, Training requirements for fall protection. Supports the statement that fall protection training covers handling and storage of equipment and materials during roofing work.
- OSHA: Protecting Roofing Workers (Publication 3755, 2015). Supports the instruction to plan ahead so that proper equipment, material and trained workers are available.